Design and Lessons Learned from the Construction of a Solider Pile and Tied- back Wall


For solider pile and lagging walls, the steel piles below the ground are generally embedded into a concrete caisson. In order to drill these caissons over 50' deep through difficult materials, the drilling rig must be very close to the hole, on a level bench. Due to the existing slope embankment and stability issues, this was not an option for this wall. We solved this problem by using driven piles, and decreased construction cost significantly. Driving piles in the existing cinder/slag fill is difficult, causing piles to twist and deflect from their intended alignment, causing construction problems. This paper discusses theoretical design and detailing issues such as: modeling of the global stability force, detailing and design of the cast-in-piace lagging and internal whalers, minimizing piles' out-of-plumb and rotation due to driving through a thick layer of cinder and slag, and etc. Also, construction issues such as: pile driving techniques and problems, achieved pile plumbness, tie-back installation and problems, under ground obstructions, concrete cast-in-place lagging, backfilling, and other lessons learned during construction will be discussed.......

【作者名称】: RAYMOND HENNEY, AHMAD K. AHMADI, SAI Consulting
【作者单位】: Engineers, Inc., Pittsburgh, PA
【关 键 词】: soldier, pile, anchor, construction, wall
【会议名称】: Engineers Society of Western Pennsylvania Annual International Bridge Conference; 20060612-14; Pittsburgh,PA(US)
【期刊论文数据库】: [DBS_Articles_01]
【期刊论文编号】: 101,685,026
【摘要长度】: 1,170
【会议地点】: Pittsburgh,PA(US)
【会议组织】: Engineers, Inc., Pittsburgh, PA
【会议时间】: 2006
【上篇论文】: 外文会议 - Lessons Learned from Failure of a Large Diameter Water Pipeline
【下篇论文】: 外文会议 - Issues Exporting a Multibody Dynamics System Model into a Finite Element Analysis Model

【论文下载】: 免费获取 该期刊&论文全文内容